30 July 2012

Reno update - #2

According to the original schedule, we would have been preparing to move back into our townhouse this coming weekend. However, due to the countertop material being delayed by three weeks (the manufacturer, Cambria, is having factory trouble), we are looking at moving back in late August instead. All the work that can be done has been done - plumbing, electrical, tile floor, kitchen cabinets, lights, and painting, There wasn’t any work done at our place all of last week because our contractor is just waiting for the counters. Sigh…

Ed and I are very happy with the work done to date and are also relieved that our design choices are visually and functionally appealing.  It's quite exciting to see it come together.
Cabinets and pot lights installed.